UCE designed the contestable works to connect two 5MW solar farms to a shared Northern Powergrid 33kV connection, including two underground cable routes.
Workers handling a large spool of pink cable outdoors.

UCE was appointed to design the contestable works associated with the connection of two 5MW Solar Farms to a common Northern Powergrid 33kV connection. Two points of connection were provided by Northern Powergrid on their overhead line circuit passing the site requiring the installation of two 33kV underground cables which over the majority of the cable route shared a common trench.

As part of the design submission Northern Powergrid requested evidence that the configuration of the cable trench would maintain the circuit rating of 37MVA.

Free Guide
The growing gap between energy awareness and demand

The whitepaper explores the growing gap between consumers’ efforts to reduce energy use and rising electricity demand, highlighting why smarter, more visible and flexible LV networks are essential as EVs, heat pumps and distributed energy resources accelerate electrification.

Download here
Consumer Energy Trends Whitepaper
Consumer Energy Trends whitepaper cover

Recent case studies

See how our solutions are empowering teams and transforming their networks to unlock capacity, prevent outages and direct investment.