Case Study: Fault Prevention With A DNO

A partial discharge service that could have saved a UK distribution network operator $300,000, and what the case shows about preventing faults.
Power distribution equipment with insulators against a clear blue sky.

The Service That Could Have Saved A DNO $300,000.

The UK has fourteen Distribution Network Operators (DNOs) based on the historic utility regions that existed before privatisation in the early 1990s. They are responsible for providing and maintaining the electricity infrastructure (cables, towers, meters) that allows the generation companies and private electricity providers to deliver power to homes and businesses.

A DNO was concerned that of one of its substations was at risk because of its riverside location. The DNO requested the installation of EA Technology’s UltraTEV Monitor to perform a long-term soak test to pick up any irregularities between routine services. The most vulnerable assets were identified and we installed the system in November 2014.

Crucially, the DNO opted not to use EA Technology’s Astute HV Monitoring Service, taking only the hardware option. That meant that any regular or continuous monitoring of the power system would be the DNO’s responsibility.

Read on to find out more…

Free Guide
The growing gap between energy awareness and demand

The whitepaper explores the growing gap between consumers’ efforts to reduce energy use and rising electricity demand, highlighting why smarter, more visible and flexible LV networks are essential as EVs, heat pumps and distributed energy resources accelerate electrification.

Download here
Consumer Energy Trends Whitepaper
Consumer Energy Trends whitepaper cover

Recent case studies

See how our solutions are empowering teams and transforming their networks to unlock capacity, prevent outages and direct investment.