Partial discharge survey of MV switchgear and transformers at SULB Company, Bahrain
-
11 September 2022
-
EA Technology
EA Technology was asked to carry out a partial discharge survey of MV switchgear and transformers at SULB, a specialised and fully integrated producer of structural steel products in the Middle East.
The survey was carried out using an UltraTEV Plus2 and UltraTEV Locator. It was the first time that a PD survey had been carried out at the plant.
Challenge
SULB wanted to incorporate online condition monitoring of their electrical assets in order to reduce the risk of insipient failures in the system.
Findings
A significant source of ultrasonic partial discharge activity was detected within the switchgear terminations at a critical 33kV substation.
The finding was immediately reported to the SULB operational manager, together with a firm recommendation to carry out an outage inspection of the switchgear terminations at the earliest opportunity.
Results
Subsequent inspection of the terminations of the switchgear identified severe damage to the HV insulation and it was clear that the switchgear was close to catastrophic failure. Due to the high risk of sudden failure and flashover, the terminations were immediately repaired under an emergency outage and the equipment returned back to service.
It is understood that the remedial work involved a temporary shutdown of plant operations for over 15 hours but it was possible to co-ordinate the activity to minimise the effect on production.
Benefits
The decision to carry out a PD survey has without doubt prevented a major electrical flashover event that would have resulted in significant damage to critical equipment, unplanned power outage across the site, high production losses and danger to operational personnel.
SULB now plan to implement partial discharge testing as a part of their routine condition assessment and maintenance activities.